Numbers, not claims.
Real projects. Actual outcomes. We do not publish estimates as results.
Manufacturing · Auto Components · Pune
From ₹38L to ₹9L annual electricity bill.
1.2 MWp rooftop solar + 500 kWh LFP battery storage commissioned for a mid-size auto-components manufacturer. DG dependency eliminated. System sized for 87% self-consumption. Payback: 4.8 years at commissioning tariff.
Capacity
1.2 MWp Solar + 500 kWh Storage
Annual generation
15.6 lakh kWh
Cost reduction
76% reduction in electricity bill
DG eliminated
Yes — complete
Payback
4.8 years
Commercial Complex · Nashik
23% reduction in common-area energy costs.
320 kWp rooftop solar installation across a 1.4 lakh sq.ft. mixed-use commercial development. Integrated with the building management system for demand optimisation. Net metering agreement secured with MSEDCL.
Capacity
320 kWp Solar
Annual generation
4.2 lakh kWh
Cost reduction
23% on common area bills
Net metering
Active
Payback
5.6 years
Building your own case study.
Start with an energy assessment. Understand your current position and the financial case for transition before any capital commitment.